Mariott Vienna

Project details

Client

S IMMO AG

Data

2 construction phases with 4 months each

  • 170 rooms in construction phase 1
  • 150 rooms in construction phase 2

Investment sum: approx. € 20 million Area: 906 m2 Spa & Wellness 16 professional companies in a small space (up to 200 workers)

DELTA Services

  • Client counseling
  • Site supervision
  • Culture management in the construction project

 

construction project Specifics

  • Rebuilding during ongoing five-star hotel operation
  • Site logistics, due to strict schedule
  • Regular and strict schedule control
  • Despite the short construction time the quality must be guaranteed
  • A defect-free handover was possible with the tool PlanRadar