Grand Opening of the Reconstructed 14th Floor of the Haemato-Oncology Clinic at University Hospital Brno

Ribbon-cutting ceremony_1_titel photo_FN Brno

University Hospital Brno has officially inaugurated the newly reconstructed 14th floor of the Department of Internal Medicine, Haematology and Oncology at University Hospital Brno and the Faculty of Medicine, Masaryk University. DELTA Group CZ was involved throughout the entire project as the designer – from the preparation of design documentation at the planning permission stage (equivalent to building permit design) and construction documentation stage, through engineering services, to design supervision.

The result is a modernised ward that fully meets the demands of contemporary medicine. The reconstruction delivered 5 intensive care beds, 5 transplantation beds and 43 standard beds, all within an environment designed with a strong emphasis on functionality, safety and comfort for both patients and medical staff.

Hospital Brno_Beds
Vyšetřovna_Medical exam table_DELTA Group CZ_14th floor_FN Brno

The project was funded through the “National Recovery and Resilience Plan” and was carried out in two phases in order to minimise disruption to the clinic’s highly specialised care. Among the technical highlights was a unique method of transporting concrete to the 14th floor – using specialised pumping equipment through window openings, which represented an exceptionally demanding construction process.

“This is another item on the long list of University Hospital Brno facilities requiring major reconstruction or refurbishment to meet today’s standards. This extraordinarily costly investment has been made possible primarily through co-financing from an EU grant programme,” said the Director of University Hospital Brno, MUDr. Ivo Rovný, MBA.

We would like to thank University Hospital Brno and all project partners for their professional collaboration. We are proud to have been part of a project that raises the quality of care for patients with haematological and oncological conditions to the next level.

Opening Brno Hospital

Key Project Data

  • Contractor: Murnyk Stav s.r.o.
  • Construction Supervision: IM Centrum, s.r.o.
  • Designer: DELTA Group CZ (Planning Permission Design, Construction Documentation, Engineering Services, Design Supervision)
  • Construction Start: 02/2025
  • Completion: 03/2026
  • Investment Cost: EUR 2,8 Mio excl. VAT

Further details on the University Hospital Brno website: Reconstruction of the inpatient ward and ICU at the Department of Internal Medicine, Haematology and Oncology