EurothermenResort Bad Schallerbach
Project Details
Client
EurothermenResort Bad Schallerbach GmbH
Facts
EurothermenResort:
- Construction Period 24 months
- Gross floor area: 15,000 m2
- 4,300 m2 therapy area
- 2,500 m2 spa baths and hotel
- 2,000 sun loungers
- 600 parking spaces
Park photovoltaic system:
- Project durationt: 10/2022 – 06/2024
- May 2024: Opening of the largest car park photovoltaic system in Upper Austria with 2,887 photovoltaic modules (= approx. 6,000 square metres)
- Construction costs of the solar park totalling 3.8 million euros
Special features
November 2024: Upper Austrian Environment and Sustainability Award 2024 for the solar park at Eurothermen Bad Schallerbach
DELTA Services
- Project management
- IT-Services
- Project planning
- Local construction supervision
Project photos: © EurothermenResorts
Photo car park photovoltaic system: © DELTA